This summer WSDOT will be repaving SR 500 from the Washougal River bridge, just south of downtown, to the intersection of SR 500 / Everett Street with SE Leadbetter Road, just north of NE 43rd Ave. 

This project will include approximately 1.2 million dollars in ADA improvements along the route. For more information see the WSDOT web page, or check the links below:

SR 500 - Camas - Paving & Sidewalk Updates 

Description: Crews will repave sections of SR 500 through Camas and improve sidewalks along the highway. 

SR 500 Both Directions  - Message boards are out to alert drivers:

 

 

 

  • July 23-27:Construction of new ADA Ramps and Electrical work on Signals
  • July 30th-August 3rd: paving work begins with the 3 bridges on the project.
  •  August 13-17 : paving mainline. 

NOTE: During construction, travelers should expect delays of up to 20 minutes, throughout the construction zone.
NOTE: All work is weather dependent. Last Updated: 7/23/2018 8:15 am. 

NOTE: During construction, travelers should expect delays of up to 20 minutes, throughout the construction zone. All work is weather dependent.

Camas Public Works News

Public Works Administration
616 NE 4th Avenue
Camas, WA  98607
360.817.1563

Operations Center
1620 SE 8th Avenue
Camas, WA  98607

Engineering
360.817.1561

Inspection Line
(to request an inspection)
360.834.8860

Sanitation
360.817.1564
hotline 360.817.1531

Street Department
360.817.1565

Water & Sewer
360.817.1567
For utility payments
or changes to accounts
360.834.2462

Waste Water Treatment Plant
1129 SE Polk Street
360.834.3263

After Hours Utility Emergencies
360.737.0592

Illicit Discharges (IDDE) Hotline
360.817.1565

Ecology
360.407.6300

Mayor's Blog

Native RTL SupportMAYORS BLOG GOES HERE

My Camas
Go to top